New solar array at Warwick Hospital

Community Energy Warwickshire has doubled the size of its solar PV arrays at Warwick Hospital after installing another 50 kWp array on the top of the new Beauchamp/Greville/Thomas ward block.

The installation was organised and completed in just over two months to help South Warwickshire NHS Foundation Trust, the owner of Warwick Hospital, to discharge a planning requirement for the new building.

After agreeing to take on the project in early October 2015, Community Energy Warwickshire specified and tendered the project, raised over £55,000 in new share capital, and appointed Eco2solar to undertake the work. With Government changes to Feed-in Tariff rates imposing tight deadlines, Eco2solar completed the installation just before Christmas.

“We are pleased we have been able to help the Trust discharge its planning obligations – and to increase the amount of solar PV capacity locally,” said Community Energy Warwickshire’s Chair, Keith Sinfield. “The Government’s plans to make major reductions to Feed-in Tariffs made it vital that we moved quickly to ensure the project was financially viable – and we are grateful to all those who invested in the project at such short notice.”

The new array brings the total solar PV capacity installed on hospitals run by South Warwickshire NHS Foundation Trust to 170 kWp.